Attention Residents and Commuters:
The Department of Transportation has provided the Village of Brewster a schedule with work that will be done between now and May 6, 2022. The schedule is as follows:
- 04/14-04/15 – Sidewalk along Carmel Ave and N. Main St
- 04/18-04/19 – Reconstruction of Michael Neuner Dr, with road closure and detour
- 04/18-04/22 – Permanent Signs and Right-of-Way fence installation
- 04/25-04/29 – Traffic Loops and pedestrian signal installation
- 04/25-04/29 – Landscaping
- 05/02-05/04 – Final Paving and striping.
UPDATE AS OF 5/3/22: Final paving will take place starting May 9, 2022. Please avoid the intersection and travel with caution while passing through the area.